A quantity takeoff is the itemized list of measured quantities for a job, each with its unit of measure, ready to be priced.

By IntelCost Team ·

A quantity takeoff is the document a takeoff produces: a list of every item of work, each with a measured quantity and a unit of measure. It is what an estimator prices, what a sub bids against, and what a reviewer checks.

What a quantity takeoff contains

Each line usually carries:

  • Item description, written the way it will be priced (for example, "Slab on grade, 4 in, 3,000 psi").
  • Quantity and unit.
  • Where it came from: the sheet, the area or the detail.
  • Classification, such as a CSI division, so the list sorts by trade.

Some firms also show waste as a separate factor, so the net measured quantity and the quantity to buy can both be seen.

Units of measure

Unit Meaning Typical items
LF Linear feet Walls, pipe, curb, trim, conduit
SF Square feet Slabs, flooring, drywall, roofing
SY Square yards Paving, carpet, seeding
CF / CY Cubic feet / cubic yards Concrete, excavation, fill
EA Each Doors, fixtures, devices
LS Lump sum Items priced as one total
TON Tons Rebar, asphalt, aggregate

The unit should match how the work is priced. Concrete is measured as an area or a length on the plan but bought by the cubic yard, so the takeoff has to convert it.

Example

Say a slab is 40 ft by 60 ft and 4 in thick (example values):

  1. Area: 40 ft x 60 ft = 2,400 SF
  2. Thickness: 4 in / 12 = 1/3 ft
  3. Volume: 2,400 SF x 1/3 ft = 800 CF
  4. Cubic yards: 800 CF / 27 = 29.6 CY
  5. With 5 percent waste (example): 29.6 CY x 1.05 = 31.1 CY

The same slab gives other lines too: 2,400 SF of vapor retarder before laps, and 200 LF of edge form around the perimeter (40 + 60 + 40 + 60 ft). One measurement, several quantities, each in its own unit. Reusable sets of lines like this are often saved as an assembly.

Net, gross and waste

  • Gross quantities are measured overall, openings included.
  • Net quantities take out openings and deducts.
  • Waste is added afterwards, item by item, because a slab and a run of trim lose material in very different ways.

Keep the three separate. A reviewer can check a net quantity against the drawings; nobody can check a number with waste already buried in it.

Quantity takeoff and pricing

Once the list is done, each line is multiplied by a unit price to reach its cost. In IntelCost, a slab's thickness is carried with the item and sub-items work out the cubic yards, the vapor retarder and the edge form from it. The concrete takeoff guide walks through slabs, footings and walls step by step.